Reminder about Utility Work (week of June 17)
Hydro One is expected to be in the area on June 17 and 18. The work will include items outlined in the previous June 5th project update:
- Digging holes for the new poles
- Installing anchors for guy wires
- Minor tree trimming required for holes and anchors
Along with:
- Pole framing
- General construction preparation for utility work
Residents can expect to see several Hydro One staff along with work vehicles such as bucket trucks and trailers. Be advised that sections of Kettleby Road will be reduced to one lane as crews move through the area.
A future update will be issued for the next phase of the utility work, including: pole removals and new installations, tree trimming/removals, moving wires and any service connection interruptions.
Share Reminder about Utility Work (week of June 17) on Facebook
Share Reminder about Utility Work (week of June 17) on Twitter
Share Reminder about Utility Work (week of June 17) on Linkedin
Email Reminder about Utility Work (week of June 17) link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends